RFQs: Showing alignment

 July 18, 2017
by Paul Heron

Our last two posts provided an overview of RFQs and the key elements in demonstrating a proponent’s capability to complete the RFP phase and, if selected, successfully fulfill the contract requirements.

If you’re not familiar with AFP/P3 processes, please read the posts linked above.

The critical importance of alignment

Beyond technical competence, a consortium needs to create confidence that it will persist through the RFP stage and will function cohesively if it wins the contract.

This is critical to the issuer. A consortium that gets shortlisted and then falls apart due to disagreements, internal issues in one or more partners, financing difficulties, or for any other reason, reduces the competitiveness of the process. If two of three shortlisted proponents drop out, the issuer must abandon a multiyear procurement—a great waste of time and money.

Poor alignment during the execution phase can cause quality, budget and schedule issues—again wasting time and money.

It’s not enough to express confidence that things will go smoothly, based on mutual respect and good intentions. With high stakes and tight schedules ahead, issuers want solid evidence.

Evidence of ability to achieve and maintain alignment

As evidence your team will stay intact and aligned, issuers will look for:

  • Experience as SPV chair: Does the head of the consortium and the designated appointee as SPV chair have a track record of steering similar teams through multiyear projects?
  • Size and strength of SPV members: Are the individual ProjectCo members large, strong companies that can provide equity and guarantees sufficient to attract the needed debt financing? Do they have the resources (people and other) to overcome unexpected setbacks?
  • Corporate relationships: Are any team members related entities? Many P3 consortiums include, for example, a financing entity and one or more construction companies with common ownership. These relationships tend to produce natural alignment.
  • Previous collaboration: Have the same companies collaborated successfully on similar projects in the past?
  • Governance structure: Are the governance structure and processes submitted in the response robust and complete? Has the SPV used the same approach successfully in similar past projects?
  • Teaming agreements: Are agreements in place to clearly identify each member’s responsibilities and decision making authority? Does the response include well-defined dispute resolution mechanisms?
  • Risk management ability: Does the RFQ response anticipate all major risks and explain how they will be managed? Are comprehensive back-to-back contracts in place to allocate risk and minimize stranded risks?

A single voice response is also evidence

Consortium proposals are, by definition, drafted by people in several companies. How do you manage the process to present a single voice response? That’s the subject of next week’s post.

 

 

 

Need help winning RFQ competitions?

Contact Complex2Clear

 

 

Photo credit


Paul Heron, MBA, is the founder and managing partner of Complex2Clear, and leads our bid response practice. LinkedIn 

 

 


  

 

Get our blog summary delivered to your inbox every month

*
*
*
How Added?:

Get future updates?:*
Privacy Policy: Complex2Clear will not use your name and contact information for any purpose other than to respond to your request and to advise you of important updates. We will not sell or give your information to any third party.
Invisifield:

Invisifield:
Top of page